Forest Park Trees Face Cuts Under Revised Plan

A hearings officer approved PGE's revised transmission project, and the appeal to City Council is due by Dec. 4.

Updated on Nov. 21, 2026 in Politics

Wide view of a cleared corridor through dense green conifer forest, with tall steel transmission towers climbing a slope above fallen timber and cut stumps in morning mist.
Portland's hearings officer approved Portland General Electric's revised plan to cut more than 370 trees in Forest Park, with appeals to City Council due by Dec. 4. AI Illustration. Upload story photo >

Live Poll

Should Portland approve utility projects that cut hundreds of trees to prevent outages?

Forest Park hikers and North and Northwest Portland electricity customers are both affected by a hearings officer's approval of Portland General Electric's revised plan to cut more than 370 trees in the park for a transmission line upgrade. The approval can still be appealed to the City Council.

Why it matters

The work is meant to prevent potential power outages in North and Northwest Portland as electricity demand grows, but it sets the utility's needs against one of the city's most valued green spaces. The council rejected an earlier version of the project in 2025, so whether this revised plan stands is an open question.

The approved revised proposal removes more than 370 trees across about 5 acres of the 5,200-acre park, and the mitigation package totals $5.5 million, which is $3.1 million above the original application. Whether the Forest Park Conservancy appeals, and how the City Council rules, remains unknown.

The players

Portland General Electric

The utility that proposed the transmission line upgrade and reached the mediation agreement with the city.

Marisha Childs

A public official named in the story in connection with the project's oversight.

The details

A city of Portland hearings officer approved PGE's revised proposal to upgrade transmission lines by rewiring an existing 1970s line and adding a second within its current right-of-way. The approval followed a mediation agreement between the city and the utility, reached more than four months earlier, that provides $5.5 million for mitigation within or adjacent to the park and requires much of it to be spent inside the project area. The hearings officer also required pre-construction wildlife surveys and timing restrictions to protect amphibians. The approval can be appealed to the City Council by Dec. 4.

Timeline

  1. June 2025: A hearings officer approved PGE's original plan.

  2. 2025: The City Council rejected the transmission project.

  3. More than four months before the approval: The city and utility reached the mediation agreement.

  4. Nov. 20, 2026: The hearings officer approved the revised proposal.

  5. Dec. 4: Deadline to appeal the approval to City Council.

Beyond the Bridges

The hearings officer's approval revisits the same transmission project the City Council rejected in 2025, now with $3.1 million more in mitigation than the original application promised. It extends that earlier fight into a revised plan, and the appeal window will show whether the council sees the changes as enough.

If you hike Forest Park or live in North or Northwest Portland, the approved work could mean visible tree removal along the transmission corridor and steadier power as demand grows. The appeal deadline of Dec. 4 is the point where residents can still weigh in through the City Council process.

The takeaway

The approval is not final until the appeal window closes or the City Council rules, so the Dec. 4 deadline is the date to watch. Residents who want to follow the project can track any appeal filed on the City Council's agenda.

What happens next

The Forest Park Conservancy's appeal decision and any City Council review must be filed by Dec. 4.

Further reading

For the council process that could take up this appeal, see City Hall coverage.

Source note: This article includes information reported by Oregon Live.

Live Poll

Should Portland approve utility projects that cut hundreds of trees to prevent outages?